Unlisted items
Water
Line item used in an appraisal estimate for design changes and to estimate pay items that have little influence on the total cost. The allowance for unlisted items in appraisal estimates should be at least 10 percent of the listed items. Line item used in a feasibility estimate for quantity changes due to receiving more design data and to estimate pay items that have little influence on the total cost. The allowance for unlisted items in a feasibility estimate varies between 2 percent and 15 percent of the listed items, depending on the form of the specifications quantities.